From 6 to 3 months behind: recovering a critical project for Primax Peru
IT Project Manager · Seratic LTDA · Primax Peru
I took over the management of an order-taking platform for Primax Peru that was six months behind schedule. The scope continued to grow as new requirements and changes were introduced in each client meeting. I stabilized the scope, reorganized execution and coordinated the development of a mobile and web solution with offline capabilities and distributor integrations, ultimately taking the product into production.
Outcome
Reduced the delay from 6 to 3 months—recovering 50% of the accumulated delay—and took the product into production through a progressive rollout across different regions of Peru.